Problem-Solving Tools - PERT Charts

 

Questions?

1-800-810-8326 or 1-802-496-5888 or email


PERT Charts

Back Up Next

PERT Charts

What It Is Used For

  • Using an activity plan as its basis, the PERT Chart is used to define the critical path of a project.

When to Use It

  • After an activity plan has been created to show the tasks needed to complete the activity and their relative timing.
  • During the implementation of the project to monitor the status.

Important Notes

  • The project team should keep a constant eye on the critical path. This is the shortest amount of time that the implementation can be completed in. If any task on the critical path slips, then the timing of the entire implementation will slip.

Back Up Next

 

PRODUCTS

SUPPORT

FREE RESOURCES

COMPANY

QualityTrainingPortal

800-810-8326

802-496-5888

Email Us

Course Catalog

Training Login

Resource Centers

About Us

Training Solutions

Knowledge Base

Contact Us

Pricing

Request Support

On-Line Store

Books/Reference Guides

Privacy Statement

2000-2016 Resource Engineering, Inc.  All rights reserved.